The Community of Madrid will carry out safety tests at weekends as part of the automation of Metro Line 6
A special free bus service will be provided to cover the affected sections via surface routes. The tests require temporary suspensions lasting 48 consecutive hours and are essential for validating all systems before the new technology is brought into service. The first events will take place on 26 and 27 September and on 3 and 4 October between Cuatro Caminos and Lucero, passing through Moncloa. This technological transformation will enable the line’s passenger capacity to be increased from the current 400,000 passengers a day to 730,000.
Over the coming weekends, until the end of the year, the Community of Madrid will carry out a programme of safety tests required to complete the automation of Metro Line 6.
In order to properly test the new systems, it will be necessary to carry out scheduled traffic closures for continuous periods of 48 hours on several sections of the route.
This phase is key to the Circular Line’s technological transformation, as it will enable the operation and integration of the various components that will make automated train services possible to be tested under controlled conditions.
The first events will take place on the weekends of 26 and 27 September and 3 and 4 October, between Cuatro Caminos and Lucero, passing through Moncloa. Both stations will remain open and will serve as temporary terminus stations for the rest of the line. These works have been scheduled for Saturday and Sunday to minimise disruption to passengers.
Whilst the underground service remains suspended, Metro de Madrid will provide users with a free replacement bus service covering the affected route via surface routes.
As the validation process progresses, Metro will provide advance notice of the following sections of the line where services will need to be temporarily suspended.
The automation of Line 6 requires the coordination of station and signalling systems with the track infrastructure and rolling stock. For this reason, an extensive testing and validation process must be completed before it is put into operation.
The tests will be carried out using two of the new automated trains, which will run along the closed section at both low and high speeds to verify the performance of the various components under different operating conditions.
On the section of the line affected by these initial works, all eight stations are now fitted with platform screen doors, and testing and fine-tuning are in their final stages, with completion expected by the end of September.
These will be joined by a further eleven of the Circular Line, which are also equipped with these devices. This means that there will be just nine left to be incorporated, a process that will be completed before the end of the year.