The Community of Madrid will complete the Metro L11 tunnel between Plaza Elíptica and Conde de Casal in 2027 and will begin work on the northern section of the Gran Diagonal

""

The draft General Budget Bill provides for a record investment of 3,374.4 million for housing, transport and infrastructure next year. The regional government will allocate more than 705 million during the coming financial year to improving and expanding regional infrastructure, an increase of 26.2 per cent compared with 2026. The Consortium will oversee the award of the new intercity bus concession map and will make progress on the management centre and season tickets linked to a digital account. The Directorate-General for Roads will put out to tender the studies required to complete the M-203 and widen the M-501, thereby improving mobility in the municipalities of the Sierra Oeste region.

In 2027, the Community of Madrid will complete the Metro Line 11 tunnel between Plaza Elíptica and Conde de Casal and will begin construction of the northern section of the future Gran Diagonal, which will link the south-west and north-east of the capital. Both measures are set out in the draft General Budget Bill for next year, which was approved today by the Governing Council and which allocates €3,374.4 million to Housing, Transport and Infrastructure.

Of this amount, more than €705 million will be allocated to the transport network, an increase of 26.2% on the previous year. A large part of this will fund new sections of the Metro de Madrid, including the extension of Line 11 and the extension of Line 5 to Adolfo Suárez Barajas Airport, both of which are currently under construction. Work will also begin on the extensions of Line 1 to Las Tablas and Madrid Nuevo Norte, as well as Lines 10 and 11 towards Móstoles and Leganés in the Poza del Agua neighbourhood.

At the same time, work will continue on the construction of the Conde de Casal and Alcalá de Henares interchanges and on the automation of the Circular line, which will increase capacity and the frequency of train services on the line most frequently used by passengers.

The Madrid Regional Transport Consortium (CRTM) expects to reach almost 1,800 million trips across the public transport network and will have a budget of 2,114 million euros in 2027, 6.7 per cent more than the previous year. The Community of Madrid will contribute more than 1.7 billion, an increase of 8 per cent, which will account for more than 80 per cent of public funding. 

In addition to providing the service, this body will draw up the Strategic Plan for Public Transport Infrastructure and Services 2027–42 and will continue with the development of the new management centre (CITRAM) and the roll-out of a system that will link tickets and season tickets to a user’s digital account (ABT). 

In 2027, the tender process for the new inter-city bus concession map will take place, with a projected investment of around €11,000 million. This initiative involves renewing the fleet and adapting lines and frequencies to passengers’ needs. 

IMPROVEMENTS TO THE ROAD NETWORK 

Furthermore, the General Budget Act allocates 38.4 million for the construction of regional roads, nearly 10 per cent more than in 2026. Consequently, the Regional Ministry of Housing, Transport and Infrastructure will continue work on the M-607, the Madrid South-East Motorway, the widening of the M-121 from Alcalá de Henares, and the link between Getafe and the M-301 at Perales del Río. 

In addition to these projects – which, together with road maintenance and improvement works, represent an investment of over €108 million – studies will be carried out throughout 2027 to make progress on other commitments announced in the latest State of the Region Address, such as completing the M-203 and widening the M-501, also known as the road of the reservoirs, to improve mobility in the municipalities of the Sierra Oeste.